Project Planning, Design & Implementation β Project Planning and Scheduling, NEC licence examination syllabus (Nepal Engineering Council).
Monitoring, Evaluation and Controlling
Measuring what has actually happened, comparing it with the plan, and doing something about the difference.
π Where this lives: The reason earned value exists is a failure mode anyone can recognise: a project has spent 50% of its budget and reports being "50% complete", and both figures are true while the project is in serious trouble β because the work actually finished is worth only 35% of the budget. Spending is not progress. Earned value analysis was developed by the US Department of Defense precisely to stop contractors reporting money spent as though it were work done. Search "earned value management schedule performance index defense".
The control cycle and its vocabulary
THE THREE ACTIVITIES ARE DISTINCT AND ARE OFTEN CONFUSED:
MONITORING β CONTINUOUS collection of data on what is
happening: progress, cost, quality, safety, risks. It
OBSERVES; it does not judge.
EVALUATION β PERIODIC, deeper assessment of whether the
project is achieving its OBJECTIVES and whether those
objectives remain valid. It asks "are we doing the right
thing?", not merely "are we on schedule?"
CONTROLLING β TAKING ACTION on the difference between plan and
actual. WITHOUT CONTROL, MONITORING IS MERELY EXPENSIVE
RECORD-KEEPING.
THE CONTROL CYCLE, which is a closed loop:
PLAN (the BASELINE)
β
EXECUTE
β
MEASURE actual performance
β
COMPARE with the baseline β VARIANCE
β
ANALYSE the cause
β
ACT β corrective action, or a formal change to the baseline
β
(back to EXECUTE)
TWO PROPERTIES OF A USEFUL CONTROL SYSTEM:
Β· IT MUST BE TIMELY. Information about a deviation is only
valuable while there is still time to act; a report
arriving after the concrete has cured is history, not
control.
Β· IT MUST COMPARE AGAINST A BASELINE. Without the approved
scope, schedule and budget, there is nothing to have a
variance from.
ββ EARNED VALUE ANALYSIS (EVA) βββββββββββββββββββββββββββββ
THE CENTRAL TECHNIQUE OF THIS TOPIC, AND THE MOST EXAMINED.
THE THREE MEASURES, at a given point in time:
PV PLANNED VALUE (BCWS) β the budgeted cost of the work
SCHEDULED to be done by now.
EV EARNED VALUE (BCWP) β the BUDGETED cost of the work
ACTUALLY COMPLETED. THIS IS THE KEY QUANTITY: it values
real progress at planned rates.
AC ACTUAL COST (ACWP) β what has actually been spent on
the work completed.
THE VARIANCES:
SCHEDULE VARIANCE SV = EV β PV
negative β BEHIND SCHEDULE
COST VARIANCE CV = EV β AC
negative β OVER BUDGET
THE INDICES, which are preferred because they are
dimensionless and comparable across projects:
SCHEDULE PERFORMANCE INDEX SPI = EV / PV
COST PERFORMANCE INDEX CPI = EV / AC
> 1 is good, < 1 is bad, for both.
A WORKED EXAMPLE β the standard exam calculation:
A project has a budget (BAC) of Rs 1,000,000 over 10 months.
At the end of month 4:
PV = Rs 400,000 (40% was scheduled)
EV = Rs 350,000 (35% is actually complete)
AC = Rs 450,000 (that is what has been spent)
SV = 350,000 β 400,000 = β Rs 50,000 BEHIND SCHEDULE
CV = 350,000 β 450,000 = β Rs 100,000 OVER BUDGET
SPI = 350,000 / 400,000 = 0.875
CPI = 350,000 / 450,000 = 0.778
READ THAT TOGETHER: THE PROJECT IS DOING 87.5% OF THE WORK
IT PLANNED AND PAYING 1/0.778 = 1.29 RUPEES FOR EVERY RUPEE
OF VALUE IT EARNS. Both are bad, and the cost problem is the
worse of the two.
NOTE WHAT A SIMPLE COST REPORT WOULD HAVE SAID: "spent
450,000 of 1,000,000, so 45% of the budget is gone at
month 4 of 10" β which sounds broadly fine. EARNED VALUE
IS WHAT REVEALS THAT ONLY 350,000 OF VALUE EXISTS FOR
THAT MONEY.
THE FORECASTS, which are what management actually wants:
ESTIMATE AT COMPLETION, assuming current efficiency
continues:
EAC = BAC / CPI = 1,000,000 / 0.7778 = Rs 1,285,714
ESTIMATE TO COMPLETE:
ETC = EAC β AC = 1,285,714 β 450,000 = Rs 835,714
VARIANCE AT COMPLETION:
VAC = BAC β EAC = β Rs 285,714
TO-COMPLETE PERFORMANCE INDEX β the efficiency now required
to finish within the original budget:
TCPI = (BAC β EV) / (BAC β AC)
= 650,000 / 550,000 = 1.182
THE TCPI IS THE REALITY CHECK: a project running at CPI 0.78
must switch to 1.18 for the remainder to hit its budget β
A 52% IMPROVEMENT IN EFFICIENCY, WHICH ALMOST NEVER
HAPPENS. THAT IS THE NUMBER THAT TELLS MANAGEMENT THE
BUDGET IS GONE, and it is why the technique is valued: it
converts a vague concern into an arithmetic impossibility.
EARNED VALUE'S KNOWN LIMITATION: SV AND SPI ARE MEASURED IN
MONEY, NOT TIME, and SPI misleadingly converges to 1.0 at the
end of a project even if it finishes late, because eventually
EV = PV = BAC. EARNED SCHEDULE is the refinement that
expresses schedule performance in time units instead.
The other tools, and evaluation
THE MONITORING TOOLS BEYOND EARNED VALUE:
S-CURVE β planned versus actual cumulative cost, as in the
life cycle topic. Simple and universally understood, but it
shows spend, not value β so it shares exactly the weakness
earned value was invented to fix.
UPDATED NETWORK / GANTT β with actual progress marked, and
THE CRITICAL PATH RECALCULATED, since it moves.
MILESTONE TRACKING β the milestone slip chart, plotting
forecast milestone dates against reporting date, makes
creeping delay unmistakable.
PROGRESS REPORTS at fixed intervals, in a fixed format.
PHYSICAL MEASUREMENT AND SITE INSPECTION β the check that
keeps the reported figures honest.
QUALITY CONTROL records, NON-CONFORMANCE reports.
RISK REGISTER REVIEW β risks reassessed, not filed and
forgotten.
CHANGE LOG.
ββ CHANGE CONTROL ββββββββββββββββββββββββββββββββββββββββββ
Every proposed change passes through a defined procedure:
1. the change is REQUESTED in writing
2. its impact on SCOPE, TIME, COST, QUALITY AND RISK is
assessed
3. it is APPROVED OR REJECTED by an authority appropriate to
its size (a CHANGE CONTROL BOARD on large projects)
4. if approved, THE BASELINE IS FORMALLY UPDATED
5. it is communicated to everyone affected
THE PURPOSE IS NOT TO PREVENT CHANGE β projects legitimately
change. IT IS TO ENSURE THAT NO CHANGE HAPPENS WITHOUT ITS
COST AND TIME BEING PRICED AND ACCEPTED FIRST. Uncontrolled
change is SCOPE CREEP, and its characteristic signature is a
project that is late and over budget with nobody able to say
which decision caused it.
ββ CORRECTIVE ACTIONS AVAILABLE ββββββββββββββββββββββββββββ
Β· reallocate resources to critical activities
Β· CRASH or FAST-TRACK, as in the scheduling topic
Β· work overtime or add shifts (with declining productivity)
Β· re-sequence the remaining work
Β· reduce scope, with the client's agreement
Β· accept the delay and formally re-baseline
Β· in the extreme, TERMINATE the project
THE PRINCIPLE: ACT ON THE CRITICAL PATH, since action anywhere
else changes the end date by nothing.
ββ EVALUATION ββββββββββββββββββββββββββββββββββββββββββββββ
Distinct from monitoring, and conducted at intervals:
FORMATIVE (mid-term) evaluation β during implementation, to
improve the remaining work.
SUMMATIVE (terminal) evaluation β at completion, on whether
objectives were achieved.
EX-POST evaluation β years after completion, on whether the
benefits actually materialised. THE MOST NEGLECTED AND THE
MOST INFORMATIVE, because it is the only one that tests
the FEASIBILITY STUDY'S PREDICTIONS against reality. A
road built to carry 5,000 vehicles a day that carries
1,200 was appraised wrongly, and only an ex-post
evaluation will ever say so.
THE STANDARD EVALUATION CRITERIA β the OECD-DAC framework used
by essentially every development agency working in Nepal:
RELEVANCE β was it the right thing to do?
COHERENCE β does it fit with other interventions?
EFFECTIVENESS β were the objectives achieved?
EFFICIENCY β were resources used economically?
IMPACT β what wider changes resulted?
SUSTAINABILITYβ will the benefits continue after the
project ends?
SUSTAINABILITY IS THE CRITERION MOST OFTEN FAILED IN
PRACTICE: a water supply scheme built successfully, handed
over, and non-functional in three years because no
maintenance funding or trained operator was arranged. THE
PROJECT SUCCEEDED AND THE INVESTMENT FAILED.
THE LOGICAL FRAMEWORK (LOGFRAME) is the standard instrument,
setting out INPUTS β ACTIVITIES β OUTPUTS β OUTCOMES β IMPACT,
each with OBJECTIVELY VERIFIABLE INDICATORS, MEANS OF
VERIFICATION and ASSUMPTIONS. Required by most donors funding
projects in Nepal.
ββ IN THE NEPALI PUBLIC SYSTEM βββββββββββββββββββββββββββββ
Β· The NATIONAL PLANNING COMMISSION monitors development
projects.
Β· The Ministry of Finance tracks budget release and
expenditure.
Β· The OFFICE OF THE AUDITOR GENERAL audits after the fact
and publishes an annual report.
Β· NATIONAL PRIDE PROJECTS receive high-level monitoring.
Β· A RECURRENT FINDING ACROSS AUDITOR GENERAL REPORTS is
LOW CAPITAL EXPENDITURE ABSORPTION with a heavy
concentration of spending in the final month of the
fiscal year β evidence that monitoring exists but control
is weak, since the pattern repeats annually without being
corrected.
Earned value's whole contribution is separating money spent from work done. A conventional report saying "45% of the budget is gone at month 4 of 10" sounds unremarkable; EV reveals that only Rs 350,000 of value exists for Rs 450,000 spent, and TCPI turns that into the flat statement that finishing on budget now requires a 52% efficiency improvement.
π Go further: Sustainability is the evaluation criterion that fails most often in Nepal, and it fails after everyone has gone home. A water supply scheme can be built to specification, commissioned, handed over and formally counted as a successful project β and be non-functional within three years because no maintenance budget was established, no operator was trained, and no local body accepted responsibility for spare parts. By every criterion the project succeeded; the investment failed. This is precisely why ex-post evaluation matters and why it is almost never funded: it is the only exercise that would reveal the gap, and nobody's performance is measured on it. Search "sustainability rural water supply schemes post-construction functionality Nepal".
π‘ Exam angle: distinguish monitoring, evaluation and controlling clearly β this definitional question comes up on its own. Draw the control cycle as a closed loop and stress that control needs a baseline and timeliness. Earned value is the calculation to master: define PV, EV and AC, compute SV, CV, SPI and CPI, interpret the signs, and produce the forecasts EAC = BAC/CPI, ETC, VAC and TCPI. Describe change control and list corrective actions, noting that action must be on the critical path. For evaluation, give the types (formative, summative, ex-post) and the OECD-DAC criteria, and mention the logframe.
Syllabus points
Project monitoring & control
Create a free account to tick topics off, take notes as you read, watch the video lessons and get a day-by-day study plan built around your exam date.