Project Planning, Design & Implementation β Project Planning and Scheduling, NEC licence examination syllabus (Nepal Engineering Council).
Project Life Cycle Phases
Every project passes through the same four stages β and the ability to influence the outcome falls as the money committed rises.
π Where this lives: The single most useful idea in this topic is the crossing curves: the ability to influence a project's outcome is highest at the very beginning, when almost nothing has been spent, and near zero at the end, when almost everything has been. This is why a day spent on the design brief is worth more than a month spent on site, and why clients who defer decisions to "sort out during construction" reliably pay several times over for them. Search "cost of change curve project life cycle influence".
The four phases
THE GENERIC PROJECT LIFE CYCLE, which every framework describes
with slightly different names and the same content:
ββββββββββββ¬ββββββββββββ¬ββββββββββββββββββ¬βββββββββββ
β INITIATIONβ PLANNING β EXECUTION β CLOSURE β
β (concept) β (design) β (implementationβ β
β β β + control) β β
ββββββββββββ΄ββββββββββββ΄ββββββββββββββββββ΄βββββββββββ
low rising HIGHEST falling
effort effort effort/spend effort
ββ 1. INITIATION / CONCEPTION ββββββββββββββββββββββββββββββ
THE QUESTION: SHOULD THIS PROJECT EXIST AT ALL?
ACTIVITIES:
Β· identify the need or opportunity
Β· PRE-FEASIBILITY STUDY β a coarse screening
Β· FEASIBILITY STUDY β technical, economic, financial,
environmental, social and legal viability
Β· define objectives and preliminary scope
Β· identify stakeholders
Β· preliminary cost estimate (Β±30% or worse)
Β· appraisal by NPV / IRR / B-C ratio
Β· ENVIRONMENTAL IMPACT ASSESSMENT (IEE or EIA), which in
Nepal is a legal precondition for many project categories
OUTPUT: THE PROJECT CHARTER (or approval document), which
formally authorises the project and names the project
manager.
THE GATE: GO / NO-GO. THIS IS THE CHEAPEST POINT AT WHICH TO
CANCEL A BAD PROJECT, and cancelling here is a success of
the process, not a failure of it.
ββ 2. PLANNING / DEFINITION ββββββββββββββββββββββββββββββββ
THE QUESTION: HOW EXACTLY WILL IT BE DONE?
ACTIVITIES:
Β· detailed DESIGN and specifications
Β· WORK BREAKDOWN STRUCTURE (WBS) β decomposing the scope
Β· scheduling: CPM / PERT network, Gantt chart
Β· resource planning and levelling
Β· detailed cost estimate (Β±10%) and BUDGET / cash flow
Β· procurement plan and tender documents
Β· RISK REGISTER and response plans
Β· quality plan, safety plan, communication plan
Β· organisation structure and responsibility matrix
OUTPUT: THE PROJECT MANAGEMENT PLAN AND THE BASELINE β
the approved scope, schedule and budget against which all
later performance is measured.
WITHOUT A BASELINE THERE IS NO CONTROL, only observation.
ββ 3. EXECUTION AND CONTROL ββββββββββββββββββββββββββββββββ
THE QUESTION: IS IT GOING TO PLAN, AND IF NOT, WHAT DO WE DO?
THE PHASE THAT CONSUMES MOST OF THE MONEY AND MOST OF THE
TIME. Two intertwined streams:
EXECUTION: procurement and contracting, mobilisation,
construction or production, quality control, supervision.
MONITORING AND CONTROL, running continuously alongside:
progress measurement, EARNED VALUE ANALYSIS, variance
analysis, CHANGE CONTROL, risk monitoring, corrective
action, reporting.
THE ESSENTIAL POINT: CONTROL IS NOT A SEPARATE LATER PHASE.
It runs concurrently with execution, because information
about a deviation is only useful while there is still time
to act on it.
ββ 4. CLOSURE / TERMINATION ββββββββββββββββββββββββββββββββ
THE QUESTION: IS IT FINISHED, AND WHAT DID WE LEARN?
ACTIVITIES:
Β· testing, commissioning and acceptance
Β· SNAG LIST / punch list and its clearance
Β· AS-BUILT DRAWINGS and operating manuals
Β· handover to the operator, and training
Β· final accounts, retention release, contract closure
Β· release of resources and team dissolution
Β· POST-PROJECT REVIEW and LESSONS LEARNED
Β· defects liability period, then final certification
THE MOST NEGLECTED PHASE IN PRACTICE. By closure the
interesting work is done, the team is being pulled onto the
next job, and the lessons-learned document β the one output
that would improve the NEXT project β is the first casualty.
AN ORGANISATION THAT NEVER COMPLETES ITS CLOSURE REVIEWS
REPEATS ITS MISTAKES INDEFINITELY, and this is the standard
exam point about closure.
The curves, and sector-specific cycles
ββ THE THREE CHARACTERISTIC CURVES βββββββββββββββββββββββββ
1. EFFORT AND COST OVER TIME β the S-CURVE.
Cumulative expenditure plotted against time is S-shaped:
slow at first (design and mobilisation), STEEP IN THE MIDDLE
(main construction), flattening at the end (finishing and
closeout).
THE S-CURVE IS THE STANDARD PROGRESS CONTROL TOOL: plot the
planned S-curve as the baseline, plot actual spend against
it, and the gap is immediately visible. A project tracking
BELOW the curve may be behind schedule β or may simply be
spending efficiently, which is why S-curve variance must be
read alongside physical progress, never alone.
2. INFLUENCE VERSUS COST OF CHANGE β THE CROSSING CURVES, and
THE MOST IMPORTANT DIAGRAM IN THIS TOPIC:
high ββ² ABILITY TO INFLUENCE β± COST OF
β β² β± CHANGES
β β² β±
β β² β±
β β² β±
β β²____________________β±
low β β± β²___
ββββββββββββββββββββββββββββββββββββΆ
initiation planning execution closure
THE ABILITY TO CHANGE THE OUTCOME IS HIGHEST AT THE START
AND FALLS CONTINUOUSLY. THE COST OF MAKING A CHANGE IS
LOWEST AT THE START AND RISES CONTINUOUSLY.
Moving a door on a drawing costs an eraser. Moving it
during construction costs demolition and rebuilding.
Moving it after handover costs that plus disruption to an
operating building.
THE MANAGERIAL CONCLUSION: SPEND DISPROPORTIONATE EFFORT
EARLY. Front-end loading β investing heavily in feasibility
and design before committing to construction β is
consistently associated with better project outcomes, and
it is exactly what pressure to "get on site" undermines.
3. RISK AND UNCERTAINTY β highest at the start, falling as
information accumulates.
CONVERSELY, THE AMOUNT AT STAKE RISES throughout. These two
curves cross as well, and their product β risk exposure β
is greatest somewhere in the middle.
ββ SECTOR-SPECIFIC LIFE CYCLES βββββββββββββββββββββββββββββ
CONSTRUCTION (RIBA-style stages):
inception β feasibility β outline design β detailed design β
tender β construction β commissioning β handover β
defects liability β operation
SOFTWARE: the SDLC of the software engineering subject β
requirements β design β implementation β testing β
deployment β maintenance, arranged as waterfall, iterative,
spiral or agile.
In NEPALI PUBLIC PROJECTS: project identification β inclusion
in the periodic plan β DPR (DETAILED PROJECT REPORT)
preparation β budget allocation β procurement under the
Public Procurement Act β implementation β completion β
audit by the Office of the Auditor General.
NOTE THE DPR: IN NEPAL, A PROJECT WITHOUT AN APPROVED
DETAILED PROJECT REPORT CANNOT PROCEED TO BUDGET, and
inadequate DPRs are a frequently cited cause of
implementation delay in Auditor General reports.
ββ PHASE GATES βββββββββββββββββββββββββββββββββββββββββββββ
Between phases sit GATES (stage gates, kill points): formal
reviews at which the project is authorised to continue, sent
back, or CANCELLED.
THE PURPOSE OF A GATE IS TO MAKE CANCELLATION POSSIBLE. A
project without gates can only be stopped by a crisis, which
guarantees it will be stopped late and expensively.
GATES ARE THE INSTITUTIONAL DEFENCE AGAINST THE SUNK COST
FALLACY described in the cash flow topic.
The crossing curves are the idea to carry away: influence over the outcome is highest when nothing has been spent, and the cost of changing anything is lowest at exactly the same moment. Every hour of design effort deferred to "sort out on site" is bought at several times its price β which is why front-end loading consistently correlates with better project outcomes.
π Go further: Closure's neglect has a name and a documented cost. Organisations that skip the post-project review lose the only output that would have improved the next project, and the pattern is visible in Nepal's Auditor General reports, which cite the same categories of failure β inadequate DPRs, land acquisition not settled before award, unrealistic schedules β year after year across different agencies. The failures are not novel; they are unlearned. This is the practical argument for treating lessons learned as a deliverable with a named owner and a deadline, rather than as something the team will write up if there is time. Search "post project review lessons learned organizational learning construction".
π‘ Exam angle: name the four phases and list the key activities and outputs of each β project charter from initiation, the baseline from planning, lessons learned from closure. Stress that monitoring and control run concurrently with execution, not after it. Draw and explain the S-curve and, above all, the influence versus cost-of-change crossing curves, since that diagram is frequently asked for by itself. Mention phase gates and that their purpose is to make cancellation possible. For Nepali context, know the DPR requirement and that projects are audited by the Office of the Auditor General.